Construction Schedule & Activity Updates
Project Update: Week of September 20, 2024
With the approach of autumn, constructions crews are focused on making the roofs and exterior walls of the building weathertight to allow interior work to continue in appropriate moisture and temperature conditions. Permanent roofing is being installed, along with vapor barriers and window caulking.
General Schedule
The general contractor managing day-to-day activity on this project is Cranshaw Construction, based in Newton Lower Falls. Founded in 1983, the company has built more than 35 million square feet of space in Boston and its surrounding metro area.
Construction is expected to be completed in March 2025. This page will provide regular updates on site activity.
Here is a general outline of what to expect in the months ahead:
September to December 2024 - In the final four months of 2024, crews working under the direction of Cranshaw Construction will be completing the structural framing for the building and making it weather tight so that work cam continue inside during inclement weather.
Permanent roofing will be completed, and dry wall will be installed, followed by painting and the installation of doors and flooring in choreographed sequence. The elevator and rooftop mechanical components also will be put into place, along with the installation of exterior siding.
Inspections to confirm that construction is adhering to Passive House environmental standards will continue throughout the process.