top of page

Construction Schedule & Activity Updates

Project Update: Week of July 21, 2024

Various types of construction work is underway on both sections of the apartment building. Wood walls and trusses continue to be placed on upper floors, while apartment bathroom plumbing, fire protection conduits, spray foam insulation and sheetrock are being installed on lower floors. 

3rd floor wall panels.jpg
5th floor trusses.jpg
staging.jpg
roughing fire proection.jpg
2nd fl unit bathroom prep.jpg
sheetrock 2nd floor corridor.jpg

General Schedule

The general contractor managing day-to-day activity on this project is Cranshaw Construction, based in Newton Lower Falls. Founded in 1983, the company has built more than 35 million square feet of space in Boston and its surrounding metro area. 

 

Construction is expected to be completed in March 2025. This page will provide regular updates on site activity.

 

Here is a general outline of what to expect in the months ahead:

 

November 2023 to January 2024 - The foundation for the building will be dug and installed, along with utility conduits. Exterior walls, stairwells, elevator pits and other concrete forms will be poured.

 

January to March 2024 - The podium for the building - meaning the first floor infrastructure, flooring systems and wall structures - will be installed. Residents can expect crane activity on the site during this period and through August, as other elements of the building are erected.

 

April to September 2024 - Wood framing will be installed on floors two through five. Roofing will be installed.

bottom of page