Construction Schedule & Activity Updates

Project Update: Week of June 16, 2024

Work continues to install the wood trusses, framing and plywood walls that will form the 4th floor of the community. The Burke Tumbling Academy parking lot adjacent to the property continues to be closed while crews install underground water infiltration systems to manage stormwater run-off.

Water in 1.jpg
Water in 2.jpg
manhole.jpg
plywood 4th.jpg
4th exterior.jpg
view.jpg

General Schedule

The general contractor managing day-to-day activity on this project is Cranshaw Construction, based in Newton Lower Falls. Founded in 1983, the company has built more than 35 million square feet of space in Boston and its surrounding metro area. 

 

Construction is expected to be completed in March 2025. This page will provide regular updates on site activity.

 

Here is a general outline of what to expect in the months ahead:

 

November 2023 to January 2024 - The foundation for the building will be dug and installed, along with utility conduits. Exterior walls, stairwells, elevator pits and other concrete forms will be poured.

 

January to March 2024 - The podium for the building - meaning the first floor infrastructure, flooring systems and wall structures - will be installed. Residents can expect crane activity on the site during this period and through August, as other elements of the building are erected.

 

April to September 2024 - Wood framing will be installed on floors two through five. Roofing will be installed.